The SOP Act contains a process where, if a payment claim is made and:
the claimant may choose to recover the claimed amount by either:
No Entitlement to Cross-Claim or Defence
The SOP Act provides that if a claimant makes a debt claim under the SOP Act, then the respondent is not, in those proceedings, entitled to bring any cross-claim against the claimant nor raise any defence in relation to matters arising under the construction contract. [2]
The recent Supreme Court decision of OSB Group Pty Ltd v Complete Hire & Sales Pty Ltd [2024] WASC 310 highlights that:
OSB Group Pty Ltd (OSB) asserted that it performed ‘construction work’ for Complete Hire & Sales Pty Ltd (Complete) under a ‘construct contract’. OSB issued a payment claim to Complete. Complete did not pay the payment claim.
OSB commenced proceedings to recover the payment as a statutory debt under the SOP Act by way of an application for summary judgment under Order 14 of the Rules of the Supreme Court 1971 (WA).
Serious questions to be tried
Complete opposed OSB’s application and submitted that there were serious questions to be tried, including that if Complete was not permitted to claim relief under the Australian Consumer Law 2010 (Cth) (ACL) for alleged misleading or deceptive conduct by OSB, whether there is an inconsistency between the SOP Act and Complete’s rights under the ACL such that s 27(3)(b) of the SOP Act (prohibiting any cross-claim or any defence) is invalid pursuant to section 109 of the Commonwealth Constitution to the extent of any inconsistency.[5]
Decision
Justice Musikanth stated that the legal question underpinning one of the serious questions to be tried was substantially the same as that raised in Bitannia Pty Ltd v Parkline Constructions Pty Ltd [2006] NSWCA 238, being “whether precluding a respondent in recovery proceedings brought under a State security of payment law from pursuing its rights under Commonwealth legislation in the face of misleading or deceptive conduct by a claimant gives rise to constitutional inconsistency”.[6]
Justice Musikanth held that:
OSB’s application for summary judgment was refused.
This article was written by Lauren Cook, Partner and Matthew Endo Solicitor | Projects, Infrastructure & Construction
Footnote:
[1] This is notwithstanding that the SOP Act prohibits a respondent from bringing any cross-claim against the claimant or raising any defence in relation to matters arising under the construction contract.
[2] OSB Group Pty Ltd v Complete Hire & Sales Pty Ltd [2024] WASC 310 at [13(14)-(15)]; Building and Construction Industry (Security of Payment) Act 2021 (WA) ss 27(3)(b)(i)-(ii).
[3] The relevant circumstances must exist in order for judgment to be given, being those set out in s 27(4) of the SOP Act as follows: a) the respondent's failure to respond to the payment claim by giving a payment schedule to the claimant within the time allowed for the response (s 27(4)(a)(i)); and (b) the respondent having not paid the claimed amount in full on or before the due date for the progress payment (s 27(4)(b)).
[4] Summary judgment will only be granted when there is no real question to be tried: OSB Group Pty Ltd v Complete Hire & Sales Pty Ltd [2024] WASC 310 at [24] citing Sutton Investment Pty Ltd v Realistic Investments Pty Ltd [2017] WASCA 14 [24].
[5] OSB Group Pty Ltd v Complete Hire & Sales Pty Ltd [2024] WASC 310 at [29].
[6] OSB Group Pty Ltd v Complete Hire & Sales Pty Ltd [2024] WASC 310 at [70].
[7] OSB Group Pty Ltd v Complete Hire & Sales Pty Ltd [2024] WASC 310 at [72].